Recycling

Title: Study of existing waste management in City of Bjelovar and municipalities Kapela, Nova Rača, Rovišće, Severin, Šandrovac, Velika Pisanica, Veliko Trojstvo and Zrinski Topolovac
Investor: Komunalac d.o.o., Krste Frankopana 24, Bjelovar (Municipal waste company)
Godina izrade: 2003.
15.369.000 kn (1st and 2nd phase)
-
Goalj: Introduction of primary recycling, separated collection of some useful and hazardous waste components in analyzed region .
Description of study:

In the first phase of the project, the preparation of technical documentation, studies, analysis are planned, but also:

  • implementation of works on choice of microlocations and facilities and equipment for first phase (paper, glass, PET, recycling yard (RY), green waste compost facility, battery storage)
  • preparation of technical documentation (RY, storage, compost facility), and implementation if possible

All preparation work for implementation of collection subsystems and actions listed below should be done in later stage of first phase:

  • for separated beverage cans collection subsystem
  • for separated collection of harmful waste via collection centers
  • for implementation of Household biowaste collection pilot program
  • Introduction and implementation of separated collection of other types of waste. We primarily would like to emphasize the increased quantities of certain types of waste such as packaging

The preparation of technical documentation for Pilot project need to start in this phase, as well as the type of treatment after year 2005 needs to be chosen

The following subsystems of collection need to be implemented until year 2005 (end of phase I):

  • separated collection of waste paper at place of generation in the containers placed on public areas in the city
  • separated collection of waste glass in containers placed on public areas in the city
  • separated collection of cardboard packaging in large packs
  • separated collection of PET packaging
  • construction of recycling yard for waste that have final user or can be temporarily stored
  • separated collection of biowaste (green waste from public areas)
  • separated collection of old motor oil in recycling yards, and in companies for collection, processing and transportation of secondary raw materials
  • separated collection of car batteries in recycling yards
  • separated collection of batteries in designated places in shops that sell batteries and in specified recycling yards

The total estimate of investment and prices for certain works and equipment for implementation of 1st phase in former municipality of Bjelovar until year 2008 is as follows:

- Estimate of needed investments in the 1st phase

separated collection in bins /containers
30.000
2.311.000
2.341.000
Recycling yard
370.000
370.000
740.000
Biowaste processing facility
1.450.000
191.000
1.641.000

Estimate of needed investment in 2nd phase

Separated collection in bins containers
0
1.095.000
1.095.000
Recycling yard
370.000
370.000
740.000
Collection centre for hazardous waste
760.000
51.000
811.000
Biowaste processing facility (qualitive and quantitive expansion)
1.000.000
7.000.000
8.000.000

The total needed investments in 1st and 2nd phase are estimated at 15,369,000 kn. It should be emphasized that these phases can be implemented gradually.. This possibility can be explained in implementation project


go to the top

Other studies conducted in last 3 years:

Title: Study on waste management and list of polluted soil and illegal waste landfill in city of Ivanić Grad and municipalities Križ and Kloštar Ivanić
Investor: IVAKOP – Ivanić Grad
Year: 2005.
10.289.000 kn
Status of study: IFinished