WASTE SORTING
|
Study
on quantity and content of municipal waste in City of
Split (summer 2005 and winter 2006 ) |
|
Čistoća d.o.o, Put Plokita
81, Split (Municipal waste company) |
|
2006. |
|
Determination of quantity and
contest of waste in order to develop most acceptable waste
management study for analyzed region |
|
Description
of study: The sampling of waste for determination of
content was performed both in summer and winter months.
It started on Monday and lasted through the workweek.
All parts of cities of Split, Kaštela and Solin that
are covered with waste collection and whose waste is
disposed on „Kerepovac“ landfill ,and waste collection
performed by „Čistoća“ from Split. The sorting activities
were coordinated with supervision of waste collection
program and weighting of waste in order to collect most
reliable data.
The determination of content was performed on waste
sorting machine placed in recycling yard of landfill
during summer period, in car maintenance shop in the
winter period. The determination of content was performed
under supervision of design engineers and municipal
waste company employees. The professional work, as well
as some operations during the sorting, was performed
by design engineers.
The sorting of waste was performed by placing waste
in sorting machine with electric rotating power motor
and sieve with openings 40 millimeters in diameter.
The waste smaller than 40 mm, fine waste felt down,
while larger pieces of waste were sorted by hand on
special table. All sorted components were weighted and
recorded and at the end of sorting of samples- the total
quantity was determined, as well as weight of each component.
The weight percentage was calculated based on weight
of sorted sample and weight of each component
The purity of material was taken into account that
sorted manually. The material that causes impurities
on pure materials are mostly humidity, dust and organic
kitchen waste, and they mostly are present on paper,
plastic bags plastic packaging, textile etc.
The following can be concluded from summer and winter
sorting of waste, as well as from data provided by municipal
waste company employees:
- he highest share of municipal
waste represents fine waste particle smaller than
40 mm with average mass share of 27,2%, out of which
85% is biodegradable component
- paper and cardboard is component
with second highest share (18,8%) , which is higher
than expected values
- organic waste from kitchen and garden has third
highest share with 17,2% and this value is somewhat
higher than average
- the plastic share (film, hard and PET packaging)
of 15,6% is higher than average values, which follows
tend of increase of plastic in general waste
- the number of organized delivery of municipal waste
transported by waste collection vehicle is 1-2 a day
- the quantity of municipal waste collected by „Ćistoća“
company from Split and disposed on „Karepovac“ landfill
is estimated at 76,780 t/year, and the quantity of
industrial waste collected and disposed is estimated
at 12,120 t/year
? 91% of permanent residents are covered with collection
of waste in observed region
? specific weight of municipal and other waste created
by permanent residents in region covered by waste
collection is 0,87 kg/resident/day
|
INVESTIGATIVE WORKS
|
Investigative
works on municipal waste landfill "Baštijunski Brig" |
|
Grad Biograd (City goverment) |
|
2006. |
| Finished |
|
In order to remediate soil,
it is necessary to conduct investigative works. The investigations
are conducted both on landfill and in labs, and collected
data are inputed in computer simulation in order to choose
the best and most economic method of remediation. The
investigations are very important since there are no hazardous
waste storages in Croatia, so more than likely some of
hazardous waste ended up on landfill. The investigation
will determine whether the hazardous waste was disposed,
in what quantities, on what locations in order to determine
the best remediation method. |
|
The landfill
was on fire most of the time, so burned waste is located
on landfill (ash and soil/ground that was used to put
out fire). Almost all flammable part of waste was burnt.
The industry was not operational or was operating with
low capacity. The conducted analysis show that the quantities
and characteristics of waste are different from the
region to region, and they also depend on seasonality.
The determination of quantity, type and characteristics
of waste is conducted in the city for some time, but
chemical-physical analyses of properties are inadequate
for definite conclusions. This is the reason why in
analysis of certain segments experiences from analysis
from developed world will be used.
Quantity, content and characteristics of waste in the
future should be analyzed as part of single waste management
system in the county, where some segments are already
in process of implementation, while others are in preparation
phase.
We will not conduct detailed analysis of waste properties,
but we will only list elements from which we can predict
and analyze what happen during waste burning and uncontrolled
disposal. These characteristics are:
- morphological content of waste
- waste humidity
- existence of certain heavy metals in the waste,
Based on last testing and calculations,
it was determined those percentages of certain waste
components are as follows:
| |
|
|
|
| |
paper |
15 |
|
| |
cloth |
4 |
|
| |
organic
waste |
30 |
|
| |
leather |
2 |
|
| |
plastic |
11 |
|
| |
rubber |
1 |
|
| |
wood |
1 |
|
| |
glass |
5 |
|
| |
metals |
2 |
|
| |
construction
material |
4 |
|
| |
hazardous
waste |
2 |
|
| |
others |
23 |
|
The humidity of waste was determined,
and is varies from 20 to 60%, while the average was
35%
The investigation that is currently conducted shoes
that in mixed municipal waste there is 1-3% of hazardous
waste such as batteries, waste color, cosmetics, hospital
waste etc
Measurements of air quality and hydro-sulphur
quantities
The measurements and analysis of
atmosphere were conducted in accordance with Air Protection
Act. The general pollution parameters were automatically
measured and analyzed every 10 minutes. The results
of measurements show that pollution never exceeded limits
allowed by law, so we expect that closest cities had
1st category quality of air. The concentration of smell
of hydro-sulphurs exceeded limit of smell, so the modeling
was conducted.
Geotechnical investigation
In order to conduct remediation
landfill, geotechnical investigations were conducted
and 3 piezometers were placed. The soil was analyzed
from drill holes as well as water on Vrana Lake. The
investigation revealed that under location there are
mainly limestone rocks and holes filled up with clay.
The water from Vrana Lake was analyzed. It was determined
that underground water is not in touch with the lake
water, so the remediation of the landfill can be conducted
by reduction of landfill area and by construction of
impermeable layer
Municipal waste analysise
U skladu s Pravilnikom o uvjetima
za postupanje s otpadom uzeti su uzorci otpada s lokacije
te je sastav eluata analiziran u laboratoriju. Uzeta
su 3 miješana uzorka izgorjelog i odležalog otpada.
Iz analiza se vidi da se radi uglavnom o inertnom otpadu
koji se skoro u potpunosti razgradio. I koncentracije
teških metala su ispod granice za odlagalište II kategorije
na koje se odlaže inertni otpad. Jedino na jednom uzorku
je ukupni organski ugljik bio iznad dozvoljene granice
za odlagalište inertnog materijala. |
STUDY OF EXISTING STATE OF WASTE MANAGEMENT
|
Study
of existing state of waste management in Slavonski Brod |
|
Grad Slavonski Brod, Vukovarska
1, Slavonski Brod (City goverment) |
|
2005. |
|
Determine existing state of
waste management as base on developing waste management
strategy in Slavonski Brod |
|
The determination
quantities of municipal waste, waste similar to municipal
waste and industrial waste in Slavonski Brod was possible
from data provided by municipal waste company from Slavonski
Brod, as well as from surveys and statistical data on
waste quantities. The determination of waste quantities
was performed for entire calendar year 2004.
The quantity of waste was determined based on data
on types and number of waste transport vehicles and
number of transport deliveries to the landfill
The total number of waste delivery to landfill Viljuš-JUG
in 2004 was 13,245. It is estimated that about 13,177
tones of waste was created, and 12,954 tones of this
waste was created by local residents.
Based on this data, the specific quantity per resident
in the area covered by waste collection was determined:
Specific quantity= 12.954 tones x 1.000/(55.320 residents
x 365 days) = 0,642 kg/resident/day
The estimated specific quantity is among average quantities.
We expect that specific quantity will rise due to increase
in standard of living.
It is also estimated that about 4,425 tones of nonhazardous
industrial waste was generated and dumped to this landfill
Some companies create smaller quantities of hazardous
industrial waste, which they store inside the company
and turnover to authorized companies for handling hazardous
waste.
The total estimated quantity of waste generated in
2004 is
| |
municipal waste |
13.177
t |
|
| |
• industrial nonhazarodus
waste |
4.425
t |
|
| |
|
|
The estimate does not include construction waste that
is not collected by municipal waste companies.
The calculation of available space on landfill location
proves the following:
The value of cumulative values of waste in 2010,without
settlement, recycling and cover material, of about 160,500
m3, will be smaller for settlement intensity under influence
if the weight of upper layers on lower layers where
microbiological decomposition is performed, but also
with activities tied to waste recycling. In this case,
the total cumulative quantity of waste is 151,000. The
25% for cover material should be added to this quantity.
Theoretically, the needed area of base for municipal
waste dumping, whose volume is about 189,000 m3 assuming
compression value of 0,75 t/m3, is about 55000 m2. The
available volume of location is about 190,000 m3, which
means that area used for remediation and continued use
is sufficient for next 5 years.
This location will be used for waste dumping until
end of 2010, by when the regional waste management centre
should be constructed. After its construction, this
landfill will be closed when 1st category landfill and
will take over function as a recycling yard, transfer
station or 2nd category landfill. All generated waste
after that will be disposed on regional landfill.
|
Our other studies (last 3 years):
IPZ Uniprojekt MCF
|
Exploratory
works- Grubišno Polje |
|
Grad Grubišno Polje (City goverment) |
|
2007. |
|
Finished |
|
Exploratory
works- Vrbanja |
|
Općina Vrbanja |
|
2007. |
|
In process of drafting |
|
Exploratory
works on landfill Dubravica- Mljet |
|
Općina Mljet |
|
2006. |
|
Finished |
|
Exploratory
works on landfill Vijuš JUG |
|
Grad Slavonski Brod |
|
2006. |
|
Finished |
|
Determination
of quantity, type and content of waste in summer period
on Landfill Buća Potok-Smiljevići- Sarajevo |
|
Kantonalno javno komunalno
preduzeće "RAD" Sarajevo, Ul. Paromlinska 57,
Sarajevo, BiH (Municipal waste company) |
|
2007. |
|
Finished |
|
Determination
of content and quantity of processed waste in Čakovec |
|
Čakom - Čakovec (Municipal
waste company) |
|
2005. |
|
Finished |
|
Determination
of content and quantity of processed waste in municipality
of Perušić |
|
Općina Perušić (Municipal goverment) |
|
2005. |
|
Finished |
|
Determination
of quantities of waste and existing state of waste management
in Osijek |
|
Grad Osijek |
|
2004. |
|
Finished |
IPZ Uniprojekt TERRA
|
Exploratory works on landfill |
|
Općina Lumbarda (Municipal
goverment) |
|
2007. |
|
Finished |
|
Exploratory
works on landfill |
|
Općina Jasenice |
|
2007. |
|
U izradi. |
|
Exploratory
works on landfill |
|
Općina Suhopolje (Municipal
goverment) |
|
2007. |
|
Finished |
|
Exploratory works on landfill "Peski"- municipality
Kloštar Podravski |
|
Općina Kloštar Podravski, Kralja
Tomislava 2, Kloštar Podravski (Municipal goverment) |
|
2007. |
|
Finished |
|
Exploratory works on landfill |
|
Općina Jakovlje |
|
2007. |
|
Finished |
|
Exploratory works |
|
Komunalac - Bjelovar |
|
2007. |
|
Finished |
|
Determination
of content and quantity of waste in Velika Gorica- summer
period |
|
Grad Velika Gorica |
|
2006. |
|
Finished |
|
Determination
of content and quantity of waste in Velika Gorica- winter
period |
|
Grad Velika Gorica |
|
2006. |
|
Finished |
|
|