Supervision
of remediation of landfill Bazjaš |
|
Vukovarsko-srijemska županija
(County government) |
| Supervision finished. Landfill
remediated. |
|
Supervision of remediation
of illegal landfill Bazjaš in order to ensure that remediation
is preformed in accordance with technical documentation
and in accordance with applicable regulations |
|
Illegal
municipal waste landfill Bazjaš was established as Vinkovci
temporary war landfill due to inability to access city
landfill in Mirkovci due to the war
1st stage of remediation- performed in 2002. on part
of landfill where waste was most at risk. It was 230
m long. The landfill was still used for municipal waste
dumping including also a part that was remediated at
the time.
2nd stage of remediation- performed on existing part
of landfill 493 m long and construction of space for
new waste dumping with waste disposal capacity large
enough to receive waste for another 18 months. During
second phase of remediation, the landfill was operational.
3rd stage of remediation (2005)- performed on leftover
122 m of landfill. At the start of this stage, the municipal
waste was not disposed on existing landfill and the
space built in 2nd phase for waste was used. The complete
remediation 854 m was finished
4th stage of remediation (2006) was performed on new
space with dimension 150*40 m and connection was built
with existing part of landfill 35 m long. The work on
remediation of the landfill "Bazjaš” 4th stage
and closing of new space were finished on December 6th
2006.
5th stage- due to the continued waste dumping on Bazjaš
after finishing 4th phase of remediation, it was necessary
to construct space 5a and 5b (5th phase of remediation).
Space could not be constructed in designed dimension
due to the fact that the construction would enter forest
area, so the area was set out in so that equal volume
of waste could be disposed. The position of new space
is between Bazjaš channel and Bazjaš forest. The final
b phase is situated between 3rd and 5 a stage
The 5th stage is constructed so the outlet channel and
fire protection area could be placed
Due to bigger size of stages 5a and 5b 6 air exhausts
were placed on 25 m distances.
Also, 5 air exhaust were raised on remediated parts
(3rd phase), due to the fact that embankment crown was
constructed on fall, and was lower than 5a and 5b embankment
crowns.
The waste was also put in compact layers, and leveling
layer of soil was placed as well
Due to the fact there was no new location for waste
disposal, the waste was disposed on this location after
the end of remediation, and the contractor raised embankment
about 1 meter on already finished leveling layer of
embankment crown. The waste was disposed here 10 days
after the end of remediation (till 25th of July 2007)
After 25th of July 2007, the final work on landfill
closing was performed until 31st of August 2007.
The remediation of landfill is finished, and main gate
were locked in order to block disposal of new waste
on this location
|